The comms room decides your weekend
Furniture can be moved twice. A network cutover cannot. Why the destination comms room is the first thing we check and the last thing most plans consider.

If an office relocation goes wrong, there is roughly a four in five chance the failure was in the comms room, and roughly a four in five chance the failure was visible weeks earlier to anyone who went and looked.
Furniture is forgiving. A desk in the wrong bay is a five minute fix on Monday morning. A network that is not testable by Sunday lunchtime is 200 people who cannot work, and there is no version of Monday that rescues it.
The readiness check
Before we confirm a shutdown date, we walk the destination comms room and complete a written check. It takes about forty minutes and it covers six things.
- Rack space: free rack units per rack, front and rear clearance, whether racks are on plinths or castors, and whether the elevation drawing matches what is physically there.
- Power: circuit count, single or three phase, C13 and C19 outlet counts, UPS capacity and actual runtime against the measured load rather than the nameplate.
- Cooling: dedicated split or in-rack, kilowatt capacity against measured heat load, and whether the condensate drain exists. This is the single most common omission.
- Floor loading: a loaded 42 RU rack regularly exceeds 800 kilograms. On a suspended slab or a raised floor that is a structural question, not a logistics one.
- Pathway: cable tray, riser access and conduit from the comms room to the floor distributors, with enough spare capacity for the patching that follows.
- Access: after-hours building access, comms room keys or cards, and a goods lift booking sized for a rack rather than a filing cabinet.
We issue the result in writing, whether or not it is welcome. A client once received a report noting their brand new comms room had no condensate drain, eleven days before the shutdown. It was an irritating Tuesday and a saved weekend.
Carrier lead times you cannot compress
This is the other half of the problem, and it is the half we cannot help with. We move equipment. We cannot move a carrier order.
As sample planning figures, Enterprise Ethernet commonly runs 20 to 40 business days from order and longer if civil works are needed. Business fibre runs 15 to 30. SIP and number porting runs 10 to 20, and once a port date is accepted it is the one date in the whole program that nobody can shift for you.
The practical consequence: order your carrier services before you sign the removals contract. We have seen an otherwise perfect relocation held up for five weeks by a lead-in that nobody ordered because everyone assumed somebody else had.
Book the carrier first, the fitout second and the removalist third. Reverse that order and the removalist becomes the person delivering the bad news.
Keep an overlap
Wherever the old lease allows, run both services in parallel for two to four weeks. An overlap turns a cutover into a migration: reversible, testable, and survivable if something is wrong. Without it, the cutover is a single irreversible event scheduled for a Saturday night, which is precisely the wrong shape for a risk of that size.
How the physical move actually runs
The comms room moves ahead of the furniture, as its own work package, so the network is testable before the first workstation lands. Racks are audited to the rack unit and photographed front and rear. Cables are labelled at both ends before anything is unplugged. Patch leads are bagged per panel. Rail kits, cage nuts and power leads stay taped to the device they belong to, because the alternative is a bucket of fixings and a very slow Saturday.
Active equipment travels in foam-lined anti-static crates, one device per cell. Full racks travel upright on air-ride suspension, strapped to the vehicle wall, on a direct run with no other consignment on board. Racks do not travel on their side, no matter how convenient the doorway makes it look.
Who owns what
We own the physical move: audit, decant, transport, re-rack and patch to an agreed schedule. Your IT team or managed service provider owns configuration, firewall rules, DNS and the logical cutover, and confirms the final backup before we power anything down.
Splitting responsibility this way is not us avoiding work. It is so that at 2:00 am on a Saturday, when something is not responding, nobody spends twenty minutes establishing whose problem it is.
More relocation notes
Standards
What AFRA accreditation actually guarantees, and what it does not
Every removalist in Australia says they are fully insured. Accreditation is the only claim on that truck that someone else has checked. Here is exactly how far it goes.
Read
Cover
Transit cover, public liability and the word 'insured'
Two different policies, two different purposes, and one word that gets used for both. The distinction decides who pays when a monitor arrives in three pieces.
Read
Records
Records, retention and the basement problem
Every long-tenanted office has a room nobody opens. A relocation is the only realistic chance you will ever get to fix it.
Read